Project: Taxiway Alpha Extension

The Taxiway Alpha Extension project represents another strategic step in enhancing the operational capacity of Albury Airport. This project will extend Taxiway Alpha at the western end of the runway, addressing operational challenges and ensuring smoother and more efficient aircraft movements during take-offs and landings.

The extension will also provide critical access to the airport's Western Precinct, a key area for the development of aviation-related businesses and services. This improvement aligns with Albury Airport’s broader infrastructure development strategy, designed to support the region’s growing aviation needs and accommodate future expansion.

Key Benefits of the Project:

  • Operational Efficiency: By reducing the need for aircraft to backtrack, the extension will streamline operations and enhance safety during aircraft movements.
  • Support for Regional Growth: The improved connectivity to the Western Precinct will facilitate the growth of aviation-related industries, strengthening Albury’s position as a regional aviation hub.
  • Alignment with Strategic Goals: As with the Taxiway Charlie Extension, this project builds on the airport’s commitment to maintaining safety, operational efficiency, and future-readiness.

The Taxiway Alpha Extension will play a pivotal role in supporting the airport’s expanding operational precinct, ensuring Albury Airport remains a critical gateway for the region and continues to meet the demands of growing air traffic and associated services.

The $2.88 million project was fully funded by the Australian Government as an identified project under the Albury Wodonga Regional Projects initiative.

Project Updates

27 October 2025

A contract for the extension of Taxiway Alpha at Albury Airport was awarded to local company Excell Gray Bruni Pty Ltd.  Construction is expected to commence in early 2026 and run for approximately 15 weeks.

9 April 2026

The extension of Taxiway Alpha at Albury Airport is now complete

Status

Complete
Airport Taxiway Alpha Extension
Airport Taxiway Alpha Extension
Airport Taxiway Alpha Extension
Airport Taxiway Alpha Extension
OUR
ACKNOWLEDGMENT

AlburyCity acknowledges the Wiradjuri people as the traditional custodians of the land in which we live and work and we pay our respects to Elders past, present and future for they hold the memories, culture, tradition and hopes of Aboriginal and Torres Strait Islander people that contribute to our community.